| Action Date | Action Description | 
|---|---|
| Feb 20, 2020 | Assent Application Received | 
| Feb 20, 2020 | Administrative Review for Completeness | 
| Feb 21, 2020 | Bio Team Review for Completeness | 
| Feb 21, 2020 | Application Accepted | 
| Feb 25, 2020 | HPHC Review Pending | 
| Feb 25, 2020 | HPHC Historical Preservation No Effect | 
| Mar 06, 2020 | Project Manager | 
| Jun 04, 2020 | Plans Received | 
| Aug 17, 2020 | Additional Information Received | 
| May 05, 2021 | Additional Information Received | 
| May 20, 2021 | Stipulation Package from Biologist | 
| May 20, 2021 | Biologist Report | 
| May 24, 2021 | Executive Sign Off | 
| May 24, 2021 | Engineering Report | 
| May 24, 2021 | Stipulation Package by Engineer | 
| May 24, 2021 | Typist for Processing | 
| May 24, 2021 | Permit Approved | 
| Aug 11, 2021 | Land Evidence Date |