| Action Date | Action Description | 
|---|---|
| Jun 25, 2020 | Maintenance Certification Request | 
| Jun 26, 2020 | Team Review for Completeness | 
| Jun 29, 2020 | Application Accepted | 
| Jul 01, 2020 | Project Manager | 
| Jul 08, 2020 | HPHC Historical Preservation No Effect | 
| Jul 08, 2020 | HPHC Review Pending | 
| Jul 13, 2020 | Biologist Report | 
| Jul 14, 2020 | Typist for Processing | 
| Jul 14, 2020 | Executive Sign Off | 
| Jul 14, 2020 | Sent to Photo Copy | 
| Jul 14, 2020 | Permit Approved |