| Action Date | Action Description | 
|---|---|
| US Army Corps of Engineers Approval Required | |
| Dock Post-Construction Certification by Engineer received. | |
| Jul 07, 2020 | Assent Application Received | 
| Jul 07, 2020 | Administrative Review for Completeness | 
| Jul 14, 2020 | Bio Team Review for Completeness | 
| Jul 14, 2020 | Deficient Application - Owner Notification Sent | 
| Jul 23, 2020 | Deficient Application Picked Up | 
| Aug 04, 2020 | Deficiency Response Received | 
| Aug 06, 2020 | Bio Team Review for Completeness | 
| Aug 06, 2020 | Application Accepted | 
| Aug 07, 2020 | Project Manager | 
| Aug 07, 2020 | Category A* (Docks) | 
| Aug 11, 2020 | Plans Received | 
| Aug 31, 2020 | HPHC Historical Preservation No Effect | 
| Aug 31, 2020 | HPHC Review Pending | 
| Oct 19, 2020 | 30 day Public Notice Issued | 
| Nov 18, 2020 | Dock Meeting -- Approval | 
| Nov 19, 2020 | Public Notice End Date | 
| Nov 23, 2020 | Biologist Report | 
| Nov 23, 2020 | Stipulation Package from Biologist | 
| Nov 23, 2020 | Typist for Processing | 
| Nov 23, 2020 | Executive Sign Off | 
| Nov 23, 2020 | Sent to Photo Copy | 
| Nov 23, 2020 | Permit Approved | 
| Dec 11, 2020 | Land Evidence Date | 
| Dec 15, 2020 | Additional Information Received |