| Action Date | Action Description | 
|---|---|
| Aug 25, 2020 | Assent Application Received | 
| Sep 01, 2020 | Administrative Review for Completeness | 
| Sep 17, 2020 | Eng Team Review for Completeness | 
| Sep 17, 2020 | Deficient Application - Owner Notification Sent | 
| Sep 22, 2020 | Deficient Application Picked Up | 
| Oct 09, 2020 | Deficiency Response Received | 
| Oct 16, 2020 | Eng Team Review for Completeness | 
| Oct 16, 2020 | Application Accepted | 
| Oct 16, 2020 | Permit Approved |