| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Sep 28, 2020 | Assent Application Received | 
| Sep 29, 2020 | Administrative Review for Completeness | 
| Sep 29, 2020 | Category A* (Docks) | 
| Oct 19, 2020 | Application Accepted | 
| Oct 19, 2020 | Bio Team Review for Completeness | 
| Oct 20, 2020 | Project Manager | 
| Oct 20, 2020 | Category A* (Docks) | 
| Oct 27, 2020 | HPHC Historical Preservation No Effect | 
| Oct 27, 2020 | HPHC Review Pending | 
| Nov 02, 2020 | Plans Received | 
| Nov 05, 2020 | 30 day Public Notice Issued | 
| Dec 05, 2020 | Public Notice End Date | 
| Jan 29, 2021 | Biologist Report | 
| Jan 29, 2021 | Mail Agenda Notice | 
| Feb 04, 2021 | Supervisor Biologist SignOff | 
| Feb 04, 2021 | Supervisor Engineer SignOff | 
| Feb 09, 2021 | Semi-Monthly Meeting Date Scheduled | 
| Feb 10, 2021 | Typist for Processing | 
| Feb 10, 2021 | Executive Sign Off | 
| Feb 10, 2021 | Sent to Photo Copy | 
| Feb 10, 2021 | Permit Approved | 
| Feb 10, 2021 | Executive Signoff of Staff Reports | 
| Feb 16, 2021 | US Army Corps of Engineers Approval Received | 
| Jan 10, 2023 | Duplicate Original Assent requested/mailed | 
| Feb 23, 2023 | Land Evidence Date |