| Action Date | Action Description | 
|---|---|
| Dec 02, 2020 | CHA Worksheet received | 
| Dec 02, 2020 | Bio Team Review for Completeness | 
| Dec 02, 2020 | Application Accepted | 
| Dec 02, 2020 | Project Manager | 
| Dec 02, 2020 | Assent Application Received | 
| Dec 02, 2020 | Administrative Review for Completeness | 
| Jan 13, 2021 | HPHC Review Pending | 
| Jan 13, 2021 | HPHC Historical Preservation No Effect | 
| Jan 19, 2021 | Plans Received | 
| Jan 22, 2021 | Stipulation Package from Biologist | 
| Jan 22, 2021 | Biologist Report | 
| Jan 25, 2021 | Typist for Processing | 
| Jan 25, 2021 | Permit Approved | 
| Jan 25, 2021 | Executive Sign Off | 
| Jan 25, 2021 | Sent to Photo Copy | 
| Feb 19, 2021 | Land Evidence Date | 
| Aug 15, 2023 | Modification Request | 
| Aug 18, 2023 | Administrative Review for Completeness | 
| Aug 23, 2023 | Bio Team Review for Completeness | 
| Aug 23, 2023 | Application Accepted | 
| Sep 12, 2023 | Biologist Report | 
| Sep 12, 2023 | Additional Information Received | 
| Sep 14, 2023 | HPHC Historical Preservation No Effect | 
| Oct 26, 2023 | Modification Approved | 
| Nov 28, 2023 | Land Evidence Date | 
| Jan 19, 2024 | Letter of Authorization | 
| Sep 04, 2024 | Note to File |