| Action Date | Action Description | 
|---|---|
| Dec 09, 2020 | Assent Application Received | 
| Dec 10, 2020 | Administrative Review for Completeness | 
| Dec 14, 2020 | Bio Team Review for Completeness | 
| Dec 14, 2020 | Application Accepted | 
| Dec 15, 2020 | Project Manager | 
| Dec 23, 2020 | HPHC Historical Preservation No Effect | 
| Dec 23, 2020 | HPHC Review Pending | 
| Feb 12, 2021 | Stipulation Package from Biologist | 
| Feb 12, 2021 | Typist for Processing | 
| Feb 12, 2021 | Executive Sign Off | 
| Feb 12, 2021 | Sent to Photo Copy | 
| Feb 12, 2021 | Permit Approved | 
| Feb 12, 2021 | Biologist Report |