| Action Date | Action Description | 
|---|---|
| Mar 23, 2021 | Assent Application Received | 
| Mar 24, 2021 | Administrative Review for Completeness | 
| Mar 29, 2021 | Category B assigned | 
| Mar 29, 2021 | Bio Team Review for Completeness | 
| Mar 29, 2021 | Application Accepted | 
| Mar 29, 2021 | Project Manager | 
| Apr 13, 2021 | HPHC Review Pending | 
| Apr 13, 2021 | 30 day Public Notice Issued | 
| Apr 13, 2021 | HPHC Historical Preservation No Effect | 
| May 11, 2021 | Comments Received | 
| May 13, 2021 | Public Notice End Date | 
| Jul 23, 2021 | Additional Information Requested from Applicant | 
| Aug 10, 2021 | Meeting Held | 
| Aug 10, 2021 | Review on Hold | 
| Mar 16, 2022 | Additional Information Received | 
| May 04, 2022 | Note to File | 
| May 09, 2022 | Additional Information Requested from Applicant | 
| May 25, 2022 | Meeting Held | 
| Jun 20, 2022 | Additional Information Received | 
| Jun 22, 2022 | Correspondence Mailed/Faxed/E-mailed | 
| Jun 22, 2022 | Additional Information Received | 
| Sep 27, 2022 | Additional Information Received | 
| Nov 29, 2022 | Additional Information Requested from Applicant | 
| Jan 06, 2023 | Additional Information Received | 
| Feb 10, 2023 | Phone Call | 
| Feb 15, 2023 | Mail Agenda Notice | 
| Feb 22, 2023 | Biologist Report | 
| Feb 22, 2023 | Engineering Report | 
| Feb 23, 2023 | Executive Signoff of Staff Reports | 
| Feb 28, 2023 | Continued Application by the Council | 
| Feb 28, 2023 | Semi-Monthly Meeting Date Scheduled | 
| Mar 06, 2023 | Mail Agenda Notice | 
| Mar 14, 2023 | Semi-Monthly Meeting Date Scheduled | 
| Mar 24, 2023 | Continued application | 
| Mar 28, 2023 | Semi-Monthly Meeting Date Scheduled | 
| Apr 04, 2023 | Mail Agenda Notice | 
| Apr 24, 2023 | Council Approval Granted | 
| Apr 24, 2023 | Semi-Monthly Meeting Date Scheduled | 
| Aug 31, 2023 | Correspondence Received | 
| Sep 06, 2023 | Legal Response/Decision | 
| Sep 14, 2023 | Typist for Processing | 
| Sep 14, 2023 | Executive Sign Off | 
| Sep 14, 2023 | Sent to Photo Copy | 
| Sep 14, 2023 | Permit Approved | 
| Sep 14, 2023 | Stipulation Package from Biologist | 
| Sep 14, 2023 | Stipulation Package by Engineer | 
| Sep 18, 2023 | Permit Mailed | 
| Sep 22, 2023 | Land Evidence Date |