| Action Date | Action Description |
|---|---|
| Monitoring Report | |
| Jul 27, 2021 | Assent Application Received |
| Jul 29, 2021 | Administrative Review for Completeness |
| Aug 11, 2021 | Note to File |
| Aug 11, 2021 | Application Accepted |
| Aug 12, 2021 | Project Manager |
| Aug 20, 2021 | HPHC Review Pending |
| Aug 20, 2021 | HPHC Historical Preservation No Effect |
| Oct 08, 2021 | Stipulation Package from Biologist |
| Oct 08, 2021 | Typist for Processing |
| Oct 08, 2021 | Executive Sign Off |
| Oct 08, 2021 | Sent to Photo Copy |
| Oct 08, 2021 | Permit Approved |
| Oct 08, 2021 | Biologist Report |
| Oct 08, 2021 | Policy Review |
| Oct 14, 2021 | Permit Mailed |
| Oct 28, 2021 | Note to File |
| Nov 02, 2021 | Land Evidence Date |
| Dec 15, 2023 | Monitoring Report |
| Aug 19, 2024 | Extension of Permit Request |
| Aug 20, 2024 | Extension Approved |
| Dec 04, 2024 | Additional Information Received |