| Action Date | Action Description |
|---|---|
| Sep 13, 2021 | Maintenance Certification Request |
| Sep 16, 2021 | Administrative Review for Completeness |
| Nov 17, 2021 | Eng Team Review for Completeness |
| Nov 17, 2021 | Application Accepted |
| Nov 17, 2021 | Project Manager |
| Nov 29, 2021 | Engineering Report |
| Dec 06, 2021 | Typist for Processing |
| Dec 06, 2021 | Executive Sign Off |
| Dec 06, 2021 | Sent to Photo Copy |
| Dec 06, 2021 | Permit Approved |
| Dec 07, 2021 | Permit Mailed |
| Dec 20, 2021 | Land Evidence Date |