| Action Date | Action Description | 
|---|---|
| Legal Response/Decision | |
| US Army Corps of Engineers Approval Required | |
| Sep 27, 2021 | Assent Application Received | 
| Sep 30, 2021 | Administrative Review for Completeness | 
| Oct 18, 2021 | US Army Corps of Engineers Approval Received | 
| Oct 22, 2021 | Application Accepted | 
| Oct 22, 2021 | Bio Team Review for Completeness | 
| Oct 26, 2021 | Project Manager | 
| Oct 26, 2021 | Category A* (Docks) | 
| Nov 05, 2021 | HPHC Review Pending | 
| Nov 05, 2021 | HPHC Historical Preservation No Effect | 
| Nov 22, 2021 | Additional Information Requested from Applicant | 
| Dec 16, 2021 | Additional Information Received | 
| Dec 21, 2021 | Comments Received | 
| Jan 13, 2022 | 30 day Public Notice Issued | 
| Feb 11, 2022 | Objections/Comments Received | 
| Feb 13, 2022 | Public Notice End Date | 
| Feb 16, 2022 | Additional Information Requested from Applicant | 
| Apr 04, 2022 | Additional Information Received | 
| May 03, 2022 | Plans Received | 
| May 10, 2022 | 30 day Public Notice Issued | 
| Jun 10, 2022 | Public Notice End Date | 
| Jun 16, 2022 | Plans Received | 
| Aug 04, 2022 | Ready to Schedule Semi-Monthly Meeting | 
| Aug 04, 2022 | Mail Agenda Notice | 
| Aug 12, 2022 | Biologist Report | 
| Aug 16, 2022 | Continued application | 
| Sep 26, 2022 | Mail Agenda Notice | 
| Oct 11, 2022 | Council Approval Granted | 
| Oct 11, 2022 | Council Approval Granted | 
| Oct 11, 2022 | Semi-Monthly Meeting Date Scheduled | 
| Oct 17, 2022 | Plans Received | 
| Oct 21, 2022 | Stipulation Package from Biologist | 
| Jan 19, 2023 | Legal Response/Decision | 
| Jan 20, 2023 | 30 Day Appeal Notification to Owner | 
| May 01, 2024 | Modification Request | 
| May 08, 2024 | Administrative Review for Completeness | 
| May 13, 2024 | Application Accepted | 
| May 13, 2024 | Project Manager | 
| May 14, 2024 | Bio Team Review for Completeness | 
| May 28, 2024 | HPHC Historical Preservation No Effect | 
| Jun 10, 2024 | Plans Received | 
| Jun 11, 2024 | Plans Received | 
| Jun 11, 2024 | 30 day Public Notice Issued | 
| Jul 11, 2024 | Public Notice End Date | 
| Aug 01, 2024 | Mail Agenda Notice | 
| Aug 05, 2024 | Entry of Appearance Received | 
| Aug 06, 2024 | Biologist Report | 
| Aug 27, 2024 | Council Approval Granted | 
| Aug 27, 2024 | Semi-Monthly Meeting Date Scheduled | 
| Sep 06, 2024 | Stipulation Package from Biologist | 
| Oct 11, 2024 | Executive Sign Off | 
| Oct 11, 2024 | Sent to Photo Copy | 
| Oct 11, 2024 | Modification Approved | 
| Oct 11, 2024 | Modification mailed | 
| Oct 11, 2024 | Typist for Processing | 
| Jan 21, 2025 | Land Evidence Date |