| Action Date | Action Description | 
|---|---|
| HPHC Review Pending | |
| Engineering Report | |
| Nov 12, 2021 | Assent Application Received | 
| Nov 15, 2021 | Administrative Review for Completeness | 
| Dec 02, 2021 | Eng Team Review for Completeness | 
| Dec 02, 2021 | Deficient Application - Owner Notification Sent | 
| Mar 01, 2024 | Deficiency Response Received | 
| Mar 12, 2024 | Eng Team Review for Completeness | 
| Mar 12, 2024 | Application Accepted | 
| Mar 12, 2024 | Project Manager | 
| Apr 12, 2024 | 30 day Public Notice Issued | 
| May 10, 2024 | 1.1.6 Meeting - tabled | 
| May 12, 2024 | Public Notice End Date | 
| Jul 10, 2024 | Dock Subcommittee Meeting Held | 
| Jul 17, 2024 | Additional Information Requested from Applicant |