| Action Date | Action Description | 
|---|---|
| Nov 16, 2021 | Assent Application Received | 
| Nov 18, 2021 | Administrative Review for Completeness | 
| Nov 18, 2021 | CHA Worksheet received | 
| Nov 24, 2021 | Eng Team Review for Completeness | 
| Nov 24, 2021 | Application Accepted | 
| Nov 29, 2021 | Project Manager | 
| Feb 24, 2022 | Plans Received | 
| Feb 25, 2022 | HPHC Historical Preservation No Effect | 
| Feb 25, 2022 | HPHC Review Pending | 
| Mar 02, 2022 | Biologist Report | 
| Mar 02, 2022 | Engineering Report | 
| Mar 07, 2022 | Typist for Processing | 
| Mar 07, 2022 | Executive Sign Off | 
| Mar 07, 2022 | Sent to Photo Copy | 
| Mar 07, 2022 | Permit Approved | 
| Mar 11, 2022 | Permit Mailed |