| Action Date | Action Description | 
|---|---|
| Nov 18, 2021 | Maintenance Certification Request | 
| Nov 22, 2021 | Administrative Review for Completeness | 
| Nov 23, 2021 | Correspondence Received | 
| Nov 29, 2021 | Eng Team Review for Completeness | 
| Nov 30, 2021 | Deficient Application - Owner Notification Sent | 
| Dec 20, 2021 | Deficiency Response Received | 
| Dec 23, 2021 | Eng Team Review for Completeness | 
| Dec 23, 2021 | Application Accepted | 
| Dec 23, 2021 | Permit Approved | 
| Dec 29, 2021 | Permit Mailed |