| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jan 04, 2022 | Assent Application Received | 
| Jan 06, 2022 | Administrative Review for Completeness | 
| Jan 28, 2022 | Category B assigned | 
| Jan 28, 2022 | Bio Team Review for Completeness | 
| Jan 28, 2022 | Application Accepted | 
| Jan 28, 2022 | Project Manager | 
| Feb 04, 2022 | 30 day Public Notice Issued | 
| Feb 07, 2022 | HPHC Review Pending | 
| Feb 07, 2022 | HPHC Historical Preservation No Effect | 
| Mar 04, 2022 | Public Notice End Date | 
| Jun 08, 2022 | US Army Corps of Engineers Approval Received | 
| Jul 18, 2022 | Biologist Report | 
| Jul 18, 2022 | Engineering Report | 
| Jul 21, 2022 | Typist for Processing | 
| Jul 21, 2022 | Permit Approved | 
| Jul 25, 2022 | Permit Mailed | 
| Jul 28, 2022 | Land Evidence Date |