| Action Date | Action Description | 
|---|---|
| Enforcement Compliance Inspection Required | |
| Jan 24, 2022 | Assent Application Received | 
| Jan 27, 2022 | Administrative Review for Completeness | 
| Feb 11, 2022 | Bio Team Review for Completeness | 
| Mar 01, 2022 | Eng Team Review for Completeness | 
| Mar 01, 2022 | Application Accepted | 
| Mar 01, 2022 | Project Manager | 
| Mar 01, 2022 | Engineering Report | 
| Mar 03, 2022 | Typist for Processing | 
| Mar 03, 2022 | Executive Sign Off | 
| Mar 03, 2022 | Sent to Photo Copy | 
| Mar 03, 2022 | Permit Approved | 
| Mar 07, 2022 | Permit Mailed | 
| Mar 21, 2022 | HPHC Historical Preservation No Effect | 
| Mar 21, 2022 | HPHC Review Pending | 
| Feb 27, 2025 | Extension of Permit Request |