| Action Date | Action Description |
|---|---|
| Jan 24, 2022 | Assent Application Received |
| Jan 27, 2022 | Administrative Review for Completeness |
| Feb 10, 2022 | Bio Team Review for Completeness |
| Feb 14, 2022 | Eng Team Review for Completeness |
| Feb 14, 2022 | Application Accepted |
| Feb 14, 2022 | Project Manager |
| Mar 04, 2022 | HPHC Review Pending |
| Mar 04, 2022 | HPHC Historical Preservation No Effect |
| Mar 17, 2022 | Additional Information Requested from Applicant |
| Apr 19, 2022 | Additional Information Received |
| Apr 19, 2022 | Plans Received |
| May 19, 2022 | Additional Information Received |
| May 19, 2022 | Engineering Report |
| May 24, 2022 | Typist for Processing |
| May 24, 2022 | Executive Sign Off |
| May 24, 2022 | Sent to Photo Copy |
| May 24, 2022 | Permit Approved |
| May 24, 2022 | Permit Mailed |
| Jun 14, 2022 | Land Evidence Date |