| Action Date | Action Description | 
|---|---|
| Feb 17, 2022 | Assent Application Received | 
| Feb 22, 2022 | Administrative Review for Completeness | 
| Feb 23, 2022 | Eng Team Review for Completeness | 
| Feb 23, 2022 | Application Accepted | 
| Feb 24, 2022 | Project Manager | 
| Feb 24, 2022 | CHA Worksheet received | 
| Mar 03, 2022 | 30 day Public Notice Issued | 
| Mar 21, 2022 | HPHC Historical Preservation No Effect | 
| Apr 03, 2022 | Public Notice End Date | 
| Apr 18, 2022 | Public Notice End Date Extension Granted | 
| Apr 25, 2022 | Comments Received | 
| Apr 26, 2022 | Engineering Report | 
| Apr 29, 2022 | Typist for Processing | 
| Apr 29, 2022 | Executive Sign Off | 
| Apr 29, 2022 | Sent to Photo Copy | 
| Apr 29, 2022 | Permit Approved | 
| May 02, 2022 | Permit Mailed | 
| May 06, 2022 | Land Evidence Date |