| Action Date | Action Description | 
|---|---|
| Mar 08, 2022 | Assent Application Received | 
| Mar 21, 2022 | Administrative Review for Completeness | 
| Mar 31, 2022 | Bio Team Review for Completeness | 
| Mar 31, 2022 | Application Accepted | 
| Mar 31, 2022 | Project Manager | 
| Apr 07, 2022 | Note to File | 
| Apr 20, 2022 | HPHC Historical Preservation No Effect | 
| May 06, 2022 | Additional Information Requested from Applicant | 
| May 06, 2022 | Note to File | 
| Jun 02, 2022 | Additional Information Received | 
| Jul 07, 2022 | Note to File | 
| Jul 08, 2022 | Additional Information Received | 
| Sep 06, 2022 | Additional Information Received | 
| Sep 08, 2022 | Correspondence Mailed/Faxed/E-mailed | 
| Dec 09, 2022 | Biologist Report | 
| Jan 05, 2023 | Typist for Processing | 
| Jan 05, 2023 | Executive Sign Off | 
| Jan 05, 2023 | Sent to Photo Copy | 
| Jan 05, 2023 | Permit Approved | 
| Jan 06, 2023 | Permit Mailed | 
| Feb 06, 2023 | Land Evidence Date | 
| Jul 27, 2023 | Commencement of Work Notice received |