| Action Date | Action Description |
|---|---|
| Mar 24, 2022 | Buffer Zone Management Application Received |
| Apr 01, 2022 | Administrative Review for Completeness |
| Apr 07, 2022 | Bio Team Review for Completeness |
| Apr 07, 2022 | Application Accepted |
| Apr 07, 2022 | Project Manager |
| Apr 28, 2022 | HPHC Review Pending |
| Apr 28, 2022 | HPHC Historical Preservation No Effect |
| May 19, 2022 | Additional Information Requested from Applicant |
| May 26, 2022 | Plans Received |
| Jun 27, 2022 | Biologist Report |
| Jul 05, 2022 | Permit Mailed |
| Jul 05, 2022 | Typist for Processing |
| Jul 05, 2022 | Executive Sign Off |
| Jul 05, 2022 | Sent to Photo Copy |
| Jul 05, 2022 | Permit Approved |
| Jul 11, 2022 | Land Evidence Date |
| Dec 09, 2022 | Monitoring Report |
| Oct 16, 2023 | Monitoring Report |