| Action Date | Action Description | 
|---|---|
| May 13, 2022 | Assent Application Received | 
| May 20, 2022 | Administrative Review for Completeness | 
| Jun 01, 2022 | Bio Team Review for Completeness | 
| Jun 01, 2022 | Application Accepted | 
| Jun 06, 2022 | Project Manager | 
| Jun 22, 2022 | HPHC Historical Preservation No Effect | 
| Jun 22, 2022 | HPHC Review Pending | 
| Jul 28, 2022 | Biologist Report | 
| Aug 04, 2022 | Typist for Processing | 
| Aug 04, 2022 | Executive Sign Off | 
| Aug 04, 2022 | Sent to Photo Copy | 
| Aug 04, 2022 | Permit Approved | 
| Aug 04, 2022 | Permit Mailed | 
| Sep 13, 2022 | Commencement of Work Notice received | 
| Oct 17, 2023 | Land Evidence Date |