| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jun 08, 2022 | Assent Application Received | 
| Jun 13, 2022 | Administrative Review for Completeness | 
| Jun 15, 2022 | Eng Team Review for Completeness | 
| Jun 15, 2022 | Application Accepted | 
| Jun 21, 2022 | Project Manager | 
| Jul 22, 2022 | HPHC Review Pending | 
| Jul 22, 2022 | HPHC Historical Preservation No Effect | 
| Nov 09, 2022 | 30 day Public Notice Issued | 
| Nov 22, 2022 | 30 day Public Notice Issued | 
| Dec 09, 2022 | Public Notice End Date | 
| Dec 22, 2022 | Public Notice End Date | 
| Jan 26, 2023 | Engineering Report | 
| Feb 02, 2023 | Typist for Processing | 
| Feb 02, 2023 | Executive Sign Off | 
| Feb 02, 2023 | Sent to Photo Copy | 
| Feb 02, 2023 | Permit Approved | 
| Feb 07, 2023 | Permit Mailed | 
| Oct 02, 2023 | Land Evidence Date |