| Action Date | Action Description | 
|---|---|
| Aug 04, 2022 | Assent Application Received | 
| Aug 11, 2022 | Administrative Review for Completeness | 
| Aug 11, 2022 | CHA Worksheet received | 
| Aug 16, 2022 | Eng Team Review for Completeness | 
| Aug 16, 2022 | Application Accepted | 
| Aug 18, 2022 | Category B assigned | 
| Aug 19, 2022 | Project Manager | 
| Aug 31, 2022 | HPHC Historical Preservation No Effect | 
| Oct 22, 2022 | Public Notice End Date | 
| Nov 02, 2022 | Water Quality Certification | 
| Feb 24, 2023 | Additional Information Received | 
| Mar 16, 2023 | Mail Agenda Notice | 
| Mar 28, 2023 | Continued application | 
| Mar 28, 2023 | Semi-Monthly Meeting Date Scheduled | 
| Apr 04, 2023 | Mail Agenda Notice | 
| Apr 24, 2023 | Semi-Monthly Meeting Date Scheduled | 
| May 18, 2023 | Engineering Report | 
| May 23, 2023 | Typist for Processing | 
| May 23, 2023 | Executive Sign Off | 
| May 23, 2023 | Sent to Photo Copy | 
| May 23, 2023 | Permit Approved | 
| Jun 23, 2023 | Permit Mailed | 
| Jun 26, 2023 | Land Evidence Date | 
| Aug 24, 2023 | Commencement of Work Notice received | 
| Apr 16, 2025 | Modification Request | 
| Apr 22, 2025 | Administrative Review for Completeness | 
| Apr 23, 2025 | Eng Team Review for Completeness | 
| Apr 23, 2025 | Project Manager | 
| Apr 23, 2025 | Application Accepted | 
| May 12, 2025 | HPHC Historical Preservation No Effect | 
| May 30, 2025 | Additional Information Received | 
| May 30, 2025 | Engineering Report | 
| Jun 17, 2025 | Typist for Processing | 
| Jun 17, 2025 | Executive Sign Off | 
| Jun 17, 2025 | Modification Approved | 
| Jun 18, 2025 | Modification mailed | 
| Jun 30, 2025 | Land Evidence Date |