| Action Date | Action Description | 
|---|---|
| Oct 03, 2022 | Maintenance Certification Request | 
| Oct 20, 2022 | Additional Information Received | 
| Oct 21, 2022 | Administrative Review for Completeness | 
| Oct 31, 2022 | Engineering Report | 
| Nov 09, 2022 | Deficient Application - Owner Notification Sent | 
| Nov 22, 2022 | Deficient Application Picked Up | 
| Jan 23, 2023 | Deficiency Response Received | 
| Feb 07, 2023 | Eng Team Review for Completeness | 
| Feb 07, 2023 | Application Accepted | 
| Feb 07, 2023 | Permit Approved | 
| Feb 08, 2023 | Permit Mailed |