| Action Date | Action Description |
|---|---|
| Dec 07, 2022 | Assent Application Received |
| Dec 12, 2022 | Administrative Review for Completeness |
| Dec 20, 2022 | Eng Team Review for Completeness |
| Dec 20, 2022 | Application Accepted |
| Dec 20, 2022 | Project Manager |
| Jan 10, 2023 | HPHC Historical Preservation No Effect |
| Jan 26, 2023 | Additional Information Received |
| Feb 07, 2023 | Engineering Report |
| Feb 20, 2023 | Typist for Processing |
| Feb 20, 2023 | Executive Sign Off |
| Feb 20, 2023 | Sent to Photo Copy |
| Feb 20, 2023 | Permit Approved |
| Feb 23, 2023 | Permit Mailed |
| Oct 16, 2023 | Additional Information Received |
| Mar 22, 2024 | Land Evidence Date |