| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jan 05, 2023 | Assent Application Received | 
| Jan 10, 2023 | Administrative Review for Completeness | 
| Jan 11, 2023 | Bio Team Review for Completeness | 
| Jan 11, 2023 | Project Manager | 
| Jan 11, 2023 | Application Accepted | 
| Jan 17, 2023 | HPHC Historical Preservation No Effect | 
| Feb 21, 2023 | 30 day Public Notice Issued | 
| Mar 17, 2023 | Objections/Comments Received | 
| Mar 23, 2023 | Public Notice End Date | 
| Aug 25, 2023 | Comments Received | 
| Aug 29, 2023 | Biologist Report | 
| Sep 06, 2023 | Mail Agenda Notice | 
| Sep 07, 2023 | Continuance Requested | 
| Sep 07, 2023 | Supervisor Biologist SignOff | 
| Sep 07, 2023 | Supervisor Engineer SignOff | 
| Sep 07, 2023 | Executive Signoff of Staff Reports | 
| Sep 11, 2023 | Continuance request by objector granted by Director | 
| Sep 12, 2023 | Semi-Monthly Meeting Date Scheduled | 
| Sep 14, 2023 | Mail Agenda Notice | 
| Sep 20, 2023 | Continuance Requested | 
| Sep 20, 2023 | Continuance Requested by Objector Denied | 
| Sep 26, 2023 | Council Approval Granted | 
| Sep 26, 2023 | Semi-Monthly Meeting Date Scheduled | 
| Feb 02, 2024 | Stipulation Package from Biologist | 
| Jul 09, 2024 | Legal Response/Decision | 
| Sep 11, 2024 | Typist for Processing | 
| Sep 11, 2024 | Executive Sign Off | 
| Sep 11, 2024 | Sent to Photo Copy | 
| Sep 11, 2024 | Permit Approved | 
| Sep 16, 2024 | Permit Mailed | 
| Sep 24, 2024 | Land Evidence Date |