| Action Date | Action Description | 
|---|---|
| Jan 10, 2023 | CHA Worksheet received | 
| Jan 10, 2023 | Assent Application Received | 
| Jan 17, 2023 | Administrative Review for Completeness | 
| Feb 08, 2023 | Eng Team Review for Completeness | 
| Feb 08, 2023 | Project Manager | 
| Feb 08, 2023 | Application Accepted | 
| Mar 10, 2023 | HPHC Historical Preservation Comments/Concerns | 
| Mar 21, 2023 | Additional Information Received | 
| Apr 26, 2023 | Additional Information Received | 
| May 16, 2023 | 30 day Public Notice Issued | 
| Jun 13, 2023 | Comments Received | 
| Jun 16, 2023 | Public Notice End Date | 
| Aug 01, 2023 | Dock/1.1.6 Review approval | 
| Sep 11, 2023 | HPHC Historical Preservation No Effect | 
| Sep 20, 2023 | Engineering Report | 
| Sep 22, 2023 | Permit Approved | 
| Sep 22, 2023 | Typist for Processing | 
| Sep 22, 2023 | Executive Sign Off | 
| Sep 22, 2023 | Sent to Photo Copy | 
| Sep 25, 2023 | Permit Mailed | 
| Oct 03, 2023 | Land Evidence Date |