| Action Date | Action Description | 
|---|---|
| Jan 17, 2023 | Assent Application Received | 
| Jan 23, 2023 | Administrative Review for Completeness | 
| Jan 24, 2023 | Bio Team Review for Completeness | 
| Jan 24, 2023 | Project Manager | 
| Jan 24, 2023 | Application Accepted | 
| Feb 17, 2023 | HPHC Historical Preservation No Effect | 
| Feb 21, 2023 | Biologist Report | 
| Mar 02, 2023 | Typist for Processing | 
| Mar 02, 2023 | Executive Sign Off | 
| Mar 02, 2023 | Sent to Photo Copy | 
| Mar 02, 2023 | Permit Approved | 
| Mar 07, 2023 | Permit Mailed | 
| Mar 28, 2023 | Land Evidence Date |