| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Feb 01, 2023 | Assent Application Received | 
| Feb 03, 2023 | Administrative Review for Completeness | 
| Feb 09, 2023 | Bio Team Review for Completeness | 
| Feb 09, 2023 | Application Accepted | 
| Feb 17, 2023 | Project Manager | 
| Feb 28, 2023 | HPHC Historical Preservation No Effect | 
| Mar 14, 2023 | 30 day Public Notice Issued | 
| Apr 14, 2023 | Public Notice End Date | 
| Aug 01, 2023 | Dock/1.1.6 Review approval | 
| Aug 15, 2023 | Additional Information Requested from Applicant | 
| Aug 31, 2023 | Correspondence Received | 
| Sep 07, 2023 | Additional Information Received | 
| Sep 13, 2023 | Biologist Report | 
| Sep 19, 2023 | Typist for Processing | 
| Sep 19, 2023 | Executive Sign Off | 
| Sep 19, 2023 | Sent to Photo Copy | 
| Sep 19, 2023 | Permit Approved | 
| Sep 25, 2023 | Permit Mailed | 
| Oct 23, 2023 | Land Evidence Date | 
| Apr 30, 2025 | Commencement of Work Notice received |