| Action Date | Action Description | 
|---|---|
| Feb 09, 2023 | CHA Worksheet received | 
| Feb 09, 2023 | Assent Application Received | 
| Feb 14, 2023 | Administrative Review for Completeness | 
| Feb 16, 2023 | Bio Team Review for Completeness | 
| Feb 16, 2023 | Application Accepted | 
| Feb 17, 2023 | Project Manager | 
| Mar 20, 2023 | HPHC Historical Preservation No Effect | 
| May 24, 2023 | Biologist Report | 
| May 26, 2023 | Typist for Processing | 
| May 26, 2023 | Executive Sign Off | 
| May 26, 2023 | Sent to Photo Copy | 
| May 26, 2023 | Permit Approved | 
| May 31, 2023 | Permit Mailed | 
| Jun 12, 2023 | Duplicate Original Assent requested/mailed | 
| Jun 21, 2023 | Land Evidence Date | 
| Jul 21, 2023 | Commencement of Work Notice received |