| Action Date | Action Description | 
|---|---|
| Assent Requirement | |
| Feb 13, 2023 | CHA Worksheet received | 
| Feb 13, 2023 | Assent Application Received | 
| Feb 17, 2023 | Administrative Review for Completeness | 
| Feb 20, 2023 | Bio Team Review for Completeness | 
| Feb 20, 2023 | Project Manager | 
| Feb 20, 2023 | Application Accepted | 
| Mar 20, 2023 | Additional Information Received | 
| Apr 26, 2023 | HPHC Historical Preservation Comments/Concerns | 
| Aug 22, 2023 | Additional Information Received | 
| Oct 04, 2023 | 30 day Public Notice Issued | 
| Oct 16, 2023 | Comments Received | 
| Nov 01, 2023 | Comments Received | 
| Nov 04, 2023 | Public Notice End Date | 
| Nov 14, 2023 | Letter of Support for Project | 
| Dec 04, 2023 | Additional Information Received | 
| Dec 11, 2023 | Additional Information Received | 
| Mar 12, 2024 | Additional Information Received | 
| May 08, 2024 | Biologist Report | 
| May 08, 2024 | HPHC Review Pending | 
| May 21, 2024 | Engineering Report | 
| May 28, 2024 | Typist for Processing | 
| May 28, 2024 | Permit Approved | 
| May 29, 2024 | Executive Sign Off | 
| May 29, 2024 | Permit Mailed | 
| Jun 06, 2024 | Land Evidence Date | 
| Mar 04, 2025 | Commencement of Work Notice received | 
| Jun 24, 2025 | Correspondence Received | 
| Jun 24, 2025 | Letter of Authorization |