| Action Date | Action Description | 
|---|---|
| Mar 13, 2023 | Maintenance Certification Request | 
| Mar 15, 2023 | Administrative Review for Completeness | 
| Apr 06, 2023 | Eng Team Review for Completeness | 
| Apr 06, 2023 | Application Accepted | 
| Apr 06, 2023 | Engineering Report | 
| Apr 11, 2023 | Typist for Processing | 
| Apr 11, 2023 | Executive Sign Off | 
| Apr 11, 2023 | Sent to Photo Copy | 
| Apr 11, 2023 | Permit Approved | 
| Apr 13, 2023 | Permit Mailed | 
| Oct 23, 2023 | Land Evidence Date |