| Action Date | Action Description | 
|---|---|
| Mar 13, 2023 | Assent Application Received | 
| Mar 16, 2023 | Administrative Review for Completeness | 
| Mar 20, 2023 | Eng Team Review for Completeness | 
| Mar 20, 2023 | Project Manager | 
| Mar 20, 2023 | Application Accepted | 
| Apr 24, 2023 | Engineering Report | 
| May 02, 2023 | Typist for Processing | 
| May 02, 2023 | Executive Sign Off | 
| May 02, 2023 | Sent to Photo Copy | 
| May 02, 2023 | Permit Approved | 
| May 04, 2023 | Permit Mailed | 
| May 10, 2023 | Correspondence Received | 
| May 10, 2023 | Land Evidence Date | 
| May 26, 2023 | HPHC Historical Preservation No Effect |