| Action Date | Action Description | 
|---|---|
| Mar 17, 2023 | Preliminary Determination Request (Coastal) | 
| Mar 21, 2023 | Administrative Review for Completeness | 
| Mar 23, 2023 | Bio Team Review for Completeness | 
| Mar 23, 2023 | Application Accepted | 
| Mar 23, 2023 | Project Manager | 
| Apr 11, 2023 | HPHC Historical Preservation No Effect | 
| May 17, 2023 | Assent Application Received | 
| May 17, 2023 | CHA Worksheet received | 
| Aug 04, 2023 | Biologist Report | 
| Aug 07, 2023 | Typist for Processing | 
| Aug 07, 2023 | Executive Sign Off | 
| Aug 07, 2023 | Sent to Photo Copy | 
| Aug 07, 2023 | Permit Approved | 
| Aug 09, 2023 | Permit Mailed | 
| Sep 19, 2023 | Land Evidence Date | 
| May 31, 2024 | Modification Request | 
| Jun 07, 2024 | Administrative Review for Completeness | 
| Jun 10, 2024 | Bio Team Review for Completeness | 
| Jun 10, 2024 | Project Manager | 
| Jun 10, 2024 | Application Accepted | 
| Jul 01, 2024 | HPHC Historical Preservation No Effect | 
| Jul 31, 2024 | Biologist Report | 
| Aug 01, 2024 | Modification Approved | 
| Aug 05, 2024 | Modification mailed | 
| Aug 26, 2024 | Land Evidence Date | 
| Sep 10, 2024 | Commencement of Work Notice received |