| Dock Post-Construction Certification by Engineer received. | |
| Mar 27, 2023 | Assent Application Received | 
| Mar 29, 2023 | Administrative Review for Completeness | 
| Mar 31, 2023 | Bio Team Review for Completeness | 
| Mar 31, 2023 | Application Accepted | 
| Mar 31, 2023 | Project Manager | 
| Apr 11, 2023 | HPHC Historical Preservation No Effect | 
| Apr 27, 2023 | Plans Received | 
| May 16, 2023 | 30 day Public Notice Issued | 
| Jun 16, 2023 | Public Notice End Date | 
| Aug 01, 2023 | Dock/1.1.6 Review approval | 
| Aug 01, 2023 | Biologist Report | 
| Aug 08, 2023 | Typist for Processing | 
| Aug 08, 2023 | Executive Sign Off | 
| Aug 08, 2023 | Sent to Photo Copy | 
| Aug 08, 2023 | Permit Approved | 
| Aug 09, 2023 | Permit Mailed | 
| Aug 25, 2023 | Land Evidence Date | 
| Mar 13, 2024 | Commencement of Work Notice received |