| Action Date | Action Description | 
|---|---|
| Mar 28, 2023 | Dredge Application | 
| Mar 28, 2023 | HPHC Historical Preservation No Effect | 
| Mar 30, 2023 | Administrative Review for Completeness | 
| Aug 10, 2023 | Eng Team Review for Completeness | 
| Aug 10, 2023 | Application Accepted | 
| Aug 25, 2023 | HPHC Historical Preservation No Effect | 
| Oct 23, 2023 | 15 day Public Notice Issued | 
| Oct 23, 2023 | Project Manager | 
| Nov 07, 2023 | Public Notice End Date | 
| Nov 30, 2023 | Typist for Processing | 
| Nov 30, 2023 | Executive Sign Off | 
| Nov 30, 2023 | Sent to Photo Copy | 
| Nov 30, 2023 | Engineering Report | 
| Dec 08, 2023 | Permit Mailed | 
| Dec 08, 2023 | Permit Approved | 
| Oct 02, 2024 | Land Evidence Date | 
| Sep 23, 2025 | Correspondence Received |