| Action Date | Action Description | 
|---|---|
| Apr 11, 2023 | Assent Application Received | 
| Apr 13, 2023 | Administrative Review for Completeness | 
| Apr 21, 2023 | Bio Team Review for Completeness | 
| Apr 25, 2023 | Application Accepted | 
| Apr 25, 2023 | Project Manager | 
| Apr 25, 2023 | Eng Team Review for Completeness | 
| May 04, 2023 | HPHC Historical Preservation No Effect | 
| May 26, 2023 | 30 day Public Notice Issued | 
| Jun 26, 2023 | Public Notice End Date | 
| Aug 01, 2023 | Dock/1.1.6 Review approval | 
| Aug 14, 2023 | Engineering Report | 
| Aug 22, 2023 | Permit Mailed | 
| Aug 22, 2023 | Typist for Processing | 
| Aug 22, 2023 | Executive Sign Off | 
| Aug 22, 2023 | Sent to Photo Copy | 
| Aug 22, 2023 | Permit Approved | 
| Oct 17, 2023 | Commencement of Work Notice received | 
| Oct 03, 2024 | Land Evidence Date |