| Action Date | Action Description | 
|---|---|
| HPHC Review Pending | |
| Apr 28, 2023 | Assent Application Received | 
| Apr 28, 2023 | CHA Worksheet received | 
| May 05, 2023 | Bio Team Review for Completeness | 
| May 05, 2023 | Project Manager | 
| May 05, 2023 | Application Accepted | 
| May 05, 2023 | Administrative Review for Completeness | 
| Jun 05, 2023 | HPHC Historical Preservation No Effect | 
| Jul 19, 2023 | Biologist Report | 
| Jul 25, 2023 | Typist for Processing | 
| Jul 25, 2023 | Executive Sign Off | 
| Jul 25, 2023 | Sent to Photo Copy | 
| Jul 25, 2023 | Permit Approved | 
| Jul 27, 2023 | Permit Mailed | 
| Oct 11, 2023 | Land Evidence Date | 
| Oct 23, 2023 | Modification Request | 
| Oct 25, 2023 | Bio Team Review for Completeness | 
| Oct 26, 2023 | Administrative Review for Completeness | 
| Nov 08, 2023 | Biologist Report | 
| Nov 08, 2023 | Typist for Processing | 
| Nov 08, 2023 | Executive Sign Off | 
| Nov 08, 2023 | Sent to Photo Copy | 
| Nov 08, 2023 | Modification Approved |