| Action Date | Action Description | 
|---|---|
| May 30, 2023 | Maintenance Certification Request | 
| Jun 05, 2023 | Administrative Review for Completeness | 
| Jun 12, 2023 | Eng Team Review for Completeness | 
| Jun 12, 2023 | Project Manager | 
| Jun 12, 2023 | Application Accepted | 
| Jun 23, 2023 | HPHC Historical Preservation No Effect | 
| Aug 21, 2023 | Plans Received | 
| Aug 28, 2023 | Engineering Report | 
| Aug 29, 2023 | Typist for Processing | 
| Aug 29, 2023 | Executive Sign Off | 
| Aug 29, 2023 | Sent to Photo Copy | 
| Aug 29, 2023 | Permit Approved | 
| Sep 06, 2023 | Permit Mailed | 
| Nov 01, 2023 | Assent Amended | 
| Nov 21, 2023 | Commencement of Work Notice received | 
| Dec 18, 2023 | Land Evidence Date |