| Action Date | Action Description | 
|---|---|
| Biologist Report | |
| Geologist Report | |
| Jul 21, 2023 | Assent Application Received | 
| Jul 28, 2023 | Administrative Review for Completeness | 
| Jul 28, 2023 | Bio Team Review for Completeness | 
| Jul 28, 2023 | Deficient Application - Owner Notification Sent | 
| Aug 24, 2023 | Phone Call | 
| Oct 19, 2023 | Deficiency Response Received | 
| Oct 27, 2023 | Bio Team Review for Completeness | 
| Oct 27, 2023 | Application Accepted | 
| Oct 27, 2023 | Project Manager | 
| Nov 07, 2023 | HPHC Historical Preservation No Effect |