| Action Date | Action Description | 
|---|---|
| Aug 16, 2023 | Maintenance Certification Request | 
| Aug 22, 2023 | Administrative Review for Completeness | 
| Sep 01, 2023 | Additional Information Received | 
| Sep 01, 2023 | Category A assigned | 
| Sep 08, 2023 | Application Accepted | 
| Sep 08, 2023 | Bio Team Review for Completeness | 
| Sep 08, 2023 | Project Manager | 
| Sep 22, 2023 | HPHC Historical Preservation No Effect | 
| Oct 19, 2023 | Additional Information Received | 
| Dec 14, 2023 | Additional Information Received | 
| Dec 15, 2023 | Typist for Processing | 
| Dec 15, 2023 | Executive Sign Off | 
| Dec 15, 2023 | Sent to Photo Copy | 
| Dec 15, 2023 | Biologist Report | 
| Dec 15, 2023 | Permit Approved | 
| Dec 19, 2023 | Permit Mailed | 
| Jan 05, 2024 | Duplicate Original Assent requested/mailed | 
| Mar 06, 2024 | Land Evidence Date | 
| Mar 22, 2024 | Commencement of Work Notice received | 
| Mar 22, 2024 | Correspondence Received | 
| Aug 30, 2024 | Assent Requirement |