| Action Date | Action Description | 
|---|---|
| Aug 25, 2023 | Assent Application Received | 
| Aug 30, 2023 | Administrative Review for Completeness | 
| Sep 08, 2023 | Bio Team Review for Completeness | 
| Sep 13, 2023 | Application Accepted | 
| Sep 13, 2023 | Project Manager | 
| Sep 13, 2023 | Eng Team Review for Completeness | 
| Oct 19, 2023 | HPHC Historical Preservation No Effect | 
| Oct 23, 2023 | Engineering Report | 
| Oct 27, 2023 | Typist for Processing | 
| Oct 27, 2023 | Executive Sign Off | 
| Oct 27, 2023 | Sent to Photo Copy | 
| Oct 27, 2023 | Permit Approved | 
| Nov 01, 2023 | Permit Mailed |