| Action Date | Action Description | 
|---|---|
| Sep 28, 2023 | Assent Application Received | 
| Oct 04, 2023 | Administrative Review for Completeness | 
| Oct 05, 2023 | Geologist Report | 
| Oct 06, 2023 | Deficient Application - Owner Notification Sent | 
| Oct 20, 2023 | Deficient Application Picked Up | 
| Oct 25, 2023 | Deficiency Response Received | 
| Oct 26, 2023 | Application Accepted | 
| Oct 26, 2023 | Project Manager | 
| Nov 14, 2023 | Geologist Report | 
| Nov 15, 2023 | Typist for Processing | 
| Nov 15, 2023 | Executive Sign Off | 
| Nov 15, 2023 | Sent to Photo Copy | 
| Nov 15, 2023 | Permit Approved | 
| Nov 17, 2023 | Permit Mailed |