| Action Date | Action Description | 
|---|---|
| Sep 29, 2023 | Assent Application Received | 
| Oct 04, 2023 | Administrative Review for Completeness | 
| Feb 20, 2024 | Deficiency - Phone Call to Applicant/Owner | 
| Apr 08, 2024 | Application Accepted | 
| Apr 08, 2024 | Project Manager | 
| Apr 08, 2024 | Bio Team Review for Completeness | 
| Apr 12, 2024 | HPHC Historical Preservation No Effect | 
| Jul 18, 2024 | Typist for Processing | 
| Jul 18, 2024 | Biologist Report | 
| Jul 22, 2024 | Executive Sign Off | 
| Jul 22, 2024 | Sent to Photo Copy | 
| Jul 22, 2024 | Permit Approved | 
| Jul 23, 2024 | Permit Mailed |