| Action Date | Action Description | 
|---|---|
| Oct 03, 2023 | Buffer Zone Management Application Received | 
| Oct 06, 2023 | Administrative Review for Completeness | 
| Oct 10, 2023 | Bio Team Review for Completeness | 
| Oct 10, 2023 | Application Accepted | 
| Oct 10, 2023 | Project Manager | 
| Oct 19, 2023 | HPHC Historical Preservation No Effect | 
| Mar 08, 2024 | Additional Information Received | 
| Mar 13, 2024 | Category M assigned | 
| Mar 13, 2024 | Biologist Report | 
| Mar 18, 2024 | Typist for Processing | 
| Mar 18, 2024 | Executive Sign Off | 
| Mar 18, 2024 | Sent to Photo Copy | 
| Mar 18, 2024 | Permit Approved | 
| Mar 20, 2024 | Permit Mailed | 
| Sep 25, 2024 | Commencement of Work Notice received |