| Action Date | Action Description | 
|---|---|
| Oct 16, 2023 | Assent Application Received | 
| Oct 20, 2023 | Administrative Review for Completeness | 
| Oct 26, 2023 | Bio Team Review for Completeness | 
| Oct 26, 2023 | Application Accepted | 
| Oct 30, 2023 | Plans Received | 
| Oct 30, 2023 | Category M assigned | 
| Nov 16, 2023 | Engineering Report | 
| Nov 16, 2023 | Project Manager | 
| Nov 22, 2023 | Typist for Processing | 
| Nov 22, 2023 | Permit Mailed | 
| Nov 22, 2023 | Executive Sign Off | 
| Nov 22, 2023 | Sent to Photo Copy | 
| Nov 22, 2023 | Permit Approved | 
| Dec 13, 2023 | Land Evidence Date |