| Action Date | Action Description | 
|---|---|
| Nov 02, 2023 | Maintenance Certification Request | 
| Nov 06, 2023 | Administrative Review for Completeness | 
| Dec 18, 2023 | Eng Team Review for Completeness | 
| Dec 18, 2023 | Application Accepted | 
| Dec 18, 2023 | Project Manager | 
| Dec 26, 2023 | Engineering Report | 
| Jan 03, 2024 | HPHC Historical Preservation No Effect | 
| Jan 05, 2024 | Executive Sign Off | 
| Jan 05, 2024 | Sent to Photo Copy | 
| Jan 05, 2024 | Permit Approved | 
| Jan 05, 2024 | Typist for Processing | 
| Jan 09, 2024 | Permit Mailed | 
| Feb 29, 2024 | Land Evidence Date |