| Action Date | Action Description | 
|---|---|
| Nov 24, 2023 | Assent Application Received | 
| Nov 28, 2023 | Administrative Review for Completeness | 
| Nov 29, 2023 | Eng Team Review for Completeness | 
| Nov 29, 2023 | Application Accepted | 
| Nov 29, 2023 | Project Manager | 
| Nov 29, 2023 | Category A* (Docks) | 
| Dec 05, 2023 | HPHC Historical Preservation No Effect | 
| Jan 02, 2024 | Plans Received | 
| Jan 10, 2024 | 30 day Public Notice Issued | 
| Feb 10, 2024 | Public Notice End Date | 
| Mar 14, 2024 | Engineering Report | 
| Mar 19, 2024 | Typist for Processing | 
| Mar 19, 2024 | Executive Sign Off | 
| Mar 19, 2024 | Sent to Photo Copy | 
| Mar 19, 2024 | Permit Approved | 
| Mar 21, 2024 | Permit Mailed | 
| Apr 09, 2024 | Commencement of Work Notice received | 
| Apr 12, 2024 | Land Evidence Date | 
| Jun 03, 2024 | Dock Post-Construction Certification by Engineer received. |