| Action Date | Action Description | 
|---|---|
| Assent Requirement | |
| Dec 07, 2023 | Buffer Zone Management Application Received | 
| Dec 11, 2023 | Administrative Review for Completeness | 
| Dec 19, 2023 | Bio Team Review for Completeness | 
| Dec 19, 2023 | Application Accepted | 
| Dec 19, 2023 | Project Manager | 
| Jan 03, 2024 | HPHC Historical Preservation No Effect | 
| Mar 18, 2024 | Biologist Report | 
| Mar 19, 2024 | Executive Sign Off | 
| Mar 19, 2024 | Sent to Photo Copy | 
| Mar 19, 2024 | Permit Approved | 
| Mar 19, 2024 | Typist for Processing | 
| Mar 21, 2024 | Permit Mailed | 
| Apr 05, 2024 | Land Evidence Date |