| Action Date | Action Description | 
|---|---|
| Monitoring Report | |
| Dec 15, 2023 | Freshwater Wetlands Application - New - received | 
| Dec 21, 2023 | Administrative Review for Completeness | 
| Jan 25, 2024 | Bio Team Review for Completeness | 
| Jan 25, 2024 | Application Accepted | 
| Jan 25, 2024 | Project Manager | 
| Jan 30, 2024 | HPHC Historical Preservation No Effect | 
| Feb 09, 2024 | Additional Information Requested from Applicant | 
| Mar 21, 2024 | Additional Information Received | 
| Apr 12, 2024 | 30 day Public Notice Issued | 
| Apr 18, 2024 | Objections/Comments Received | 
| Apr 26, 2024 | Additional Information Requested from Applicant | 
| Apr 29, 2024 | Correspondence Mailed/Faxed/E-mailed | 
| May 12, 2024 | Public Notice End Date | 
| May 13, 2024 | Plans Received | 
| May 13, 2024 | Correspondence Mailed/Faxed/E-mailed | 
| May 15, 2024 | Correspondence Mailed/Faxed/E-mailed | 
| May 21, 2024 | Correspondence Received | 
| May 24, 2024 | Correspondence Mailed/Faxed/E-mailed | 
| May 31, 2024 | Correspondence Received | 
| Jul 15, 2024 | Correspondence Mailed/Faxed/E-mailed | 
| Aug 09, 2024 | Plans Received | 
| Aug 15, 2024 | Biologist Report | 
| Aug 22, 2024 | Typist for Processing | 
| Aug 22, 2024 | Executive Sign Off | 
| Aug 22, 2024 | Sent to Photo Copy | 
| Aug 22, 2024 | Permit Approved | 
| Aug 23, 2024 | Permit Mailed | 
| Oct 09, 2024 | Land Evidence Date | 
| Jan 03, 2025 | Correspondence Mailed/Faxed/E-mailed |